Decision by the Secretary of State on an application by Chrysaor Production (UK) Limited for:
- the construction, operation and maintenance of a carbon dioxide (CO2) intake facility at Immingham
- the construction and burial of an onshore CO2 transportation pipeline to Theddlethorpe on the Lincolnshire coast
- the construction of a facility at Theddlethorpe to send the CO2 out to a subsea reservoir
Date of decision
9 April 2025
Company / location
Chrysaor Production (UK) Limited
151 Buckingham Palace Road聽
London
SW1W 9SZ
Maximum storage
The pipeline aims to transport and store up to 10 million tonnes of CO2 annually by 2030.